Contact Dec-Tam

Selective Demolition and ABATEMENT at the hanover inn  

Within the next month or so, Dec-Tam will be finishing up on site at the Hanover Inn in Hanover New Hampshire.  For the past few months, Dec-Tam was on-site averaging 80 technicians working multiple shifts 5 to 6 days per week.  The inn is undertaking a full renovation.  They are adding 12,000 square feet to the property and converting existing office space into additional guest rooms.  The inn's restaurant was also relocated during this project. 

Working in conjunction with Engelberth Construction, Dec-Tam performed the selective demolition, asbestos abatement and decontamination, and the lead paint abatement components of this job.  Once Dec-Tam and the general contractor reviewed the drawings and marked out the locations for removal, then abatement and demolition activities were performed at the Hanvoer Inn. 

As you can see from the associated pictures we removed and disposed of:

During the asbestos portion of the project we remediated and disposed of over:

A three chamber decon facility was installed at the entrance to each work areas constructed out of poly sheeting and PVC supports.  All critical barriers at each work area location were sealed with two layers of 6 mil poly sheeting.  Splash guards were installed to protect lower wall surfaces where chemical solvents were used to remove floor mastic.  Negative air pressure was establish using HEPA filters to allow for proper air changes within the containment.  These units were exhausted to the outside of the building. 

Upon completion of the project, Dec-Tam will have removed approximately 350 tons of asbestos debris and 300 tons of general construction debris from the approximately 90,000 square foot existing building. 

The Inn is expected to be reopen late Spring. 

Dartmouth benefited from having Dec-Tam do both the environmental remediation and the selective demolition because they :

< back

Project Highlights

Customer
Hanover Inn - Dartmouth College

Location
Hanover New Hampshire

Type
Building Gut - Selective Demolition - Asbestos Abatement - Lead Abatement

Project Size

90,000 Square Feet

Project Summary
Fast paced, comprehensive gut of historic inn on an expedited schedule.  At time there were  80 technicians on site, working 2 shifts for 5 to 6 days a week for ten to twelve weeks.

Selective Demolition

18 images

Hallway-Pre-demolition.jpg
Hallway-Ready-to-Go.jpg
Pre Demolition.jpg
Hallway-Demolition-in-Progress.jpg
Start-of-Guest-Room-Demo.jpg
Getting-Down-to-the-tubs.jpg
Gutting-the-Guestrooms.jpg
Final Floor of Demolition
Mechanical-Room-Predemolition.jpg
Mechanical Room Post Demo.jpg
Preparing-for-Exterior-Demo.jpg
Exterior-Paver-Demolition.jpg
Removing-Pavers-for-New-Construction.jpg
Debris ready to be hauled out.jpg
Windows-to-Plaza.jpg
Removal-of-Plaza-Windows.jpg
Removal-of-Windows-to-Plaza.jpg
The various trades during firedrill.jpg
 

DEC-TAM CORPORATION
50 Concord Street | North Reading, MA 01864-2602 | 978.470.2860
Copyright 2011 Dec-Tam Corporation. All rights reserved. | Privacy Policy | Sitemap
Website Design and Search Engine Optimization by Discovery Communications Group.